keerti c Posted April 6, 2021 Share Posted April 6, 2021 Hi Team , I have targeted dates in one column and have actually achieved dates in another column for a paticular project design review. Please help me suggest how can I see the actual and targeted on one graph. For now created 2 scatter plots need to kind of combine them but not sure if it is possible. Link to comment Share on other sites More sharing options...
Gaia Paolini Posted April 7, 2021 Share Posted April 7, 2021 What if you put actual date on the x axis and targeted date on the y axis (or vice versa). You could then draw a diagonal and see how the two dates differ by the distance of each point to the diagonal. If that does not work too well with actual dates on the axes you could try to turn them to numeric with a transformation function Link to comment Share on other sites More sharing options...
keerti c Posted April 8, 2021 Author Share Posted April 8, 2021 Thanks for your response Gaia.I will try as suggested. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now